Earned value questions

PRACTICE QUESTIONS
Music Festival
A guitar shop is putting together a local music festival. The project manager who is heading up the project wants to use earned value metrics to
calculate how well they are sticking to the budget and schedule. The following calendarized budget was created during the planning phase of the
project.
Music Festival Project
1.0 Reserve Park
1.1 Review Available Dates
1.2 Approve Festival Date and Make Deposit
2.0 Book Headline Performers
2.1 Contact Agents for Possible Headliners
2.2 Finalize Headliner Contracts
2.3 Create Posters
3.0 Vendors
3.1 Advertisement for Vendors
3.2 Review and Approve Vendor Applications
3.3 Create Map of Vendor Booth Locations
Weekly Work Totals
Week 1
Week 2
Week 3
Week 4
Week 5
Week 6
Week 7
Week 8
$2,000
$2,000
$2,000
$2,000
$3,500
$5,500
$2,000
$1,300
$9,000
$9,000
$3,100
$800
$2,100
$500
$3,900
$1,900
$31,400
$7,000
$1,800
$500
$1,200
$2,000
$5,500
Task Totals
$6,000
$3,200
At the end of week 4, what is the Planned Value of the project?
At the end of week 4, what is the Planned Value of the project, using the 50/50 rule?
At the end of week 4, what is the Planned Value of the project, using the 0/100 rule?
$2,100
$9,100
$600
$2,400
$1,100
$1,100
Playground Construction Project
An elementary school principal is working with a contractor to get a new playground installed during summer break. All the required equipment
and parts were purchased and delivered on budget before the project started. The labor estimate is $3000. During their weekly status report
meeting, the contractor gives the principal the following values from their project tracking software: Earned Value = $1200, Planned Value =
$1800, Actual Cost = $1100.
What is the project Cost Variance?
What is the project Cost Performance Index?
What is the project Estimate at Completion?
What is the project Estimate to Complete?
What is the project To Complete Performance Index?
What is the project Schedule Variance?
What is the project Schedule Performance Index?
What is the project Percent Complete Index?
ANSWER KEY
Music Festival
A guitar shop is putting together a local music festival. The project manager who is heading up the project wants to use earned value metrics to
calculate how well they are sticking to the budget and schedule. The above calendarized budget was created during the planning phase of the
project.
At the end of week 4, what is the Planned Value of the project?
$2,000 + $5,500 + $6,000 + $3,200 = $16,700
Add up the totals at the bottom of the columns for each of the first four weeks of the project.
At the end of week 4, what is the Planned Value of the project, using the 50/50 rule?
$2,000 + $2,000 + $9,000 + 50% * ($2,000 + $7,000) + $500 + (50% * ($1,200 + $2,100 + $600) =
$13,500 + 50% * $9,000 + 50% * $3,900 =
$19,950
Add up all the tasks that should be completed by the end of Week 4. Ignore all the tasks that shouldn’t start until after Week 4. Add in
50% of the total of each task that should be in progress at the end of Week 4 – the entire task total, no matter how many weeks it goes
should be included.
At the end of week 4, what is the Planned Value of the project, using the 0/100 rule?
$2,000 + $2,000 + $9,000 + $500 = $13,500
Add up all the tasks that should be completed by the end of Week 4. Ignore all the tasks that shouldn’t be completed until after Week 4.
NOTE: The same process can be used to calculate either Earned Value or Planned Value. Earned Value is based on the percent of work
completed, while Planned Value is based on the percent of work the schedule shows should be completed. That percentage times the budget is
the EV or PV for that task.
Playground Construction Project
An elementary school principal is working with a contractor to get a new playground installed during summer break. All the required equipment
and parts were purchased and delivered on budget before the project started. The labor estimate is $3000. During their weekly status report
meeting, the contractor gives the principal the following values from their project tracking software: Earned Value = $1200, Planned Value =
$1800, Actual Cost = $1100.
What is the project Cost Variance?
$1200-$1100 = $100 (the project is currently $100 under budget)
What is the project Cost Performance Index?
$1200/$1100 = 1.09 (they are receiving one dollar and nine cents’ worth of value for every dollar spent on the project)
What is the project Estimate at Completion?
$3000/1.09 = $2750 (at this rate, the project is likely to cost about $2750, which is a little bit less than originally budgeted)
What is the project Estimate to Complete?
$2750-$1100 = $1650 (they will only need $1650 more to complete the project, if they keep spending at this rate)
What is the project To Complete Performance Index?
($3000-$1200)/($3000-$1100) = $1800/$1900 = .95 (the project can get as low as 95 cents’ worth out of every dollar they spend for the
second half of the project and still come in on budget; the formula compares how much work is left to how much money is left)
What is the project Schedule Variance?
$1200-$1800 = $600 (the project needs to spend an extra $600 in labor to get caught up on the schedule)
What is the project Schedule Performance Index?
$1200/$1800 = .67 (of the work that should be completed by now, only two thirds of that is actually completed)
What is the project Percent Complete Index?
$1200/$3000 = .4 (the project is 40% complete)

Calculate the price
Make an order in advance and get the best price
Pages (550 words)
$0.00
*Price with a welcome 15% discount applied.
Pro tip: If you want to save more money and pay the lowest price, you need to set a more extended deadline.
We know how difficult it is to be a student these days. That's why our prices are one of the most affordable on the market, and there are no hidden fees.

Instead, we offer bonuses, discounts, and free services to make your experience outstanding.
How it works
Receive a 100% original paper that will pass Turnitin from a top essay writing service
step 1
Upload your instructions
Fill out the order form and provide paper details. You can even attach screenshots or add additional instructions later. If something is not clear or missing, the writer will contact you for clarification.
Pro service tips
How to get the most out of your experience with StudyAcademia.com
One writer throughout the entire course
If you like the writer, you can hire them again. Just copy & paste their ID on the order form ("Preferred Writer's ID" field). This way, your vocabulary will be uniform, and the writer will be aware of your needs.
The same paper from different writers
You can order essay or any other work from two different writers to choose the best one or give another version to a friend. This can be done through the add-on "Same paper from another writer."
Copy of sources used by the writer
Our college essay writers work with ScienceDirect and other databases. They can send you articles or materials used in PDF or through screenshots. Just tick the "Copy of sources" field on the order form.
Testimonials
See why 20k+ students have chosen us as their sole writing assistance provider
Check out the latest reviews and opinions submitted by real customers worldwide and make an informed decision.
11,595
Customer reviews in total
96%
Current satisfaction rate
3 pages
Average paper length
37%
Customers referred by a friend
OUR GIFT TO YOU
15% OFF your first order
Use a coupon FIRST15 and enjoy expert help with any task at the most affordable price.
Claim my 15% OFF Order in Chat